Moore-Hodgson Algorithm

Minimizes the number of late jobs on a single machine by dropping the longest job from overloaded prefixes.

Quick Facts

Compact metadata for implementation and discovery.

Category
Scheduling
Difficulty
Intermediate
Family
Single-Machine Scheduling
Tier
Core
Status
Verified
Review
Source Checked
Sources
2
Formulas
0
Relationships
3
Code example
Ready
Visualization
Ready

Overview

Moore-Hodgson sorts jobs by due date and scans the prefix schedule. Whenever the current prefix cannot meet its due date, it removes the longest processing-time job from that prefix.

Core Concepts

late-job minimizationsingle-machine schedulingscheduling

Quick facts

Complexity

Runtime and memory behavior at a glance.

Best

O(n)

Average

O(n log n)

Worst

O(n^2)

Space

O(n)

When to Use

  • Use when all jobs are available and the goal is minimizing the number of late jobs.
  • Use when dropped or deferred jobs can be handled separately after the on-time set is chosen.

When Not to Use

  • Avoid when jobs have weights, release times, or precedence constraints not modeled by the algorithm.
  • Avoid when every job must be scheduled even if late-job count is not the objective.

What It Does

  • Sorts jobs by due date
  • Maintains the scheduled prefix duration
  • Removes the longest job when a prefix becomes late

Use Cases

  • Single-machine scheduling with late-job count as the objective
  • Production planning where some jobs may be deferred
  • Teaching exchange arguments in scheduling

Inputs

  • Job list with processing durations p_j and due dates d_j
  • Single-machine availability window

Outputs

  • Ordered job execution sequence
  • Completion times C_j and lateness/tardiness metrics

Pseudocode

  1. 1.Sort jobs by increasing due date
  2. 2.Initialize total processing time to 0 and an empty max-heap
  3. 3.For each job, add it to the heap and add its processing time
  4. 4.If total time exceeds this job's due date, remove the longest job from the heap
  5. 5.Return jobs left in the heap as the maximum on-time set

Canonical Example

Input
jobs A(p=4,d=4), B(p=3,d=5), C(p=2,d=6)
Output
on-time jobs = B, C; late/deferred job = A
Explanation
The prefix A,B exceeds due date 5, so the longest job A is removed.

Implementation Notes

  • Sort by due date and scan in that order.
  • Use a max-heap keyed by processing time for jobs currently in the on-time prefix.
  • Record removed jobs so the final late set is explicit.

Common Pitfalls

  • Treating removed jobs as deleted rather than late or deferred work.
  • Using the shortest job instead of the longest job for removal breaks the greedy rule.
  • Forgetting to maintain total prefix processing time after removals.

Interactive Mechanism Walkthrough

Graph Frontier & Edge Relaxation

Show sorting by due date and removing the longest job when deadlines are missed on a small late-job minimization example.

Moore-Hodgson Algorithm mechanism walkthrough step 1 of 5suvwxt
Step 1 of 5: Sort jobs by increasing due date
scheduling-mechanism

Notes

The algorithm chooses an on-time subset; it does not optimize the order of the late jobs.

Sources (2)

What each reference supports for this entry.

Scheduling: Theory, Algorithms, and Systems

Book

Scheduling reference for Moore-Hodgson single-machine late-job minimization and due-date ordered job selection.

Moore Late-Jobs Sequencing Algorithm

Paper

Original reference for minimizing the number of late jobs on one machine, including the Moore-Hodgson scheduling procedure.

Open source

Explore Next

Good next jumps from the relationship graph, ranked for useful discovery.

Moore-Hodgson scans jobs in earliest-due-date order.

A max-priority queue removes the longest job from an overloaded prefix.