Overview
Latest Finish Time scheduling works backward through a dependency graph to identify slack and critical tasks.
Computes how late each task can finish without delaying the project.
Compact metadata for implementation and discovery.
Latest Finish Time scheduling works backward through a dependency graph to identify slack and critical tasks.
Quick facts
Runtime and memory behavior at a glance.
Best
O(V + E)
Average
O(V + E)
Worst
O(V + E)
Space
O(V)
LF(task) = min LS(successor)A task must finish before the earliest latest-start time of its successors.
Show jobs on a timeline with queue order, start times, and constraints.
Latest Finish Time should be used with the assumptions and tradeoffs of project Scheduling in mind.
What each reference supports for this entry.
Scheduling reference for Latest Finish Time precedence, due-date, lateness, or project-schedule optimization.
Good next jumps from the relationship graph, ranked for useful discovery.
Latest-finish and earliest-start times are paired quantities in critical-path scheduling analysis.